Request a Proposal
Renewables

2.0 MW Interior UPS skid

Location(s)

Numerous Locations

Dimensions

8.5’ x 22’

Power

2.0 MW

Highlights

40+ units deployed / RAF and Overhead Product

Tactics Employed

Project focus related to footprint and logistics for moving into deeper interior spaces. The design allowed for 80% of the work to be performed outside of the critical path of receiving equipment. This project represented a step into buy vs. build, which takes traditional trade work and shifts it to another subcontractor’s scope of work.

Lessons Learned

Incorporate everything possible into the factory rather than the field. These products have several vendor-installed components that are done at startup, but can easily be installed and tested prior to shipping. This helps avoid issues with parts getting lost offsite, and saves time if anything goes wrong.

Have a Project?

Would You Like to Work on Projects Like This?

Start-to-Finish
Attention.

Our team focuses on the entire lifecycle of your project, ensuring that nothing is overlooked.

Our Services

Full System
Solutions.

When designing your system, we take a global view of the entire process and every possible component.

Products

Newsletter Sign-up