Dimensions

24' x 42'

Power

2.4MW

N+1 HVAC via Chilled Water CRAH and WSHP

Tactics Employed

The manufacturing team was engaged prior to design being completed for this site, along with two others. As each room was developed, the site teams coordinated around receiving the completed buildings.

Lessons Learned

Site logistics can cripple the plan if not addressed early in the process. Key elements such as crane and rigging paths, and related plans, are critical when using large-scale offsite methods.