UPS Environmental Enclosure

Dimensions

20' x 50'

Power

2.0MW

N HVAC Units – CRAH

Tactics Employed

This project had a very short schedule, and entailed working out of sequence. Most of the components were assembled prior to equipment being received, to accommodate rapid assembly.

Lessons Learned

On shorter-duration project implementations, coordination with the site becomes critical. There were existing conditions that had to be accounted for in order to execute a proper offsite plan. This reinforces the DFMA mentality, and why it is so critical to design the site to the product, rather than the product to the site.

Have a Project?

Get in touch with our business development team and we’ll contact you as soon as possible.

Start-to-Finish
Attention.

Our team focuses on the entire lifecycle of your project, ensuring that nothing is overlooked.

Our Services

Full System
Solutions.

When designing your system, we take a global view of the entire process and every possible component.

Products

Careers

Where Every Individual Matters and Every Goal Is Possible.