UPS Environmental Enclosure
Dimensions
20' x 50'
Power
2.0MW
N HVAC Units – CRAH
Tactics Employed
This project had a very short schedule, and entailed working out of sequence. Most of the components were assembled prior to equipment being received, to accommodate rapid assembly.
Lessons Learned
On shorter-duration project implementations, coordination with the site becomes critical. There were existing conditions that had to be accounted for in order to execute a proper offsite plan. This reinforces the DFMA mentality, and why it is so critical to design the site to the product, rather than the product to the site.